Three projects could change how Cocoa Village looks and works by 2030. They are an eight-story apartment building on Brevard Avenue, a seven-story hotel a block away and a Brightline station. If you're comparing Cocoa with other Space Coast options, you'll probably hear about all three. Each one is at a different stage. The apartment developer has asked for a rebate of part of the new property tax its own building would create, and any similar request for the hotel would have to go through its own separate application.
That kind of incentive affects the timing as much as the cost. A tax rebate only pays out after a building is finished and assessed. So the city's money follows the construction instead of starting it, and the timeline depends on financing, permits and votes that are still ahead. If you're paying for a home near the Village partly because of what's coming, here's where each project stands.
How the Rebate Works on 430 Brevard Avenue
The biggest proposal is at 430 Brevard Avenue, a 1.95-acre block that city staff described as blighted after Bank of America left. The applicant, 430 Brevard, LLC, is identified in the staff memo as The Framework Group. It proposes a building up to eight stories and 238,270 square feet, with at least 242 market-rate apartments ranging from studios to three-bedrooms, plus 2,800 square feet of ground-floor retail. The application includes 25 covered parking spaces for Cocoa Village visitors, gated off from resident parking.
The developer estimates the cost at about $93 million. That includes $4.5 million for land and $72.8 million in direct construction. Staff reported 43.97 percent owner equity, more than double the program's 20 percent minimum, with The Barclay Group named as capital partner.
Here's the request. For 10 years, the Cocoa Community Redevelopment Agency would pay the developer 90 percent of the new property tax increment the project creates inside the CRA district. Staff projects those payments at about $6.23 million. The CRA would keep the other 10 percent, about $692,000 over the same decade. Today the land produces about $15,000 a year in increment.
Those numbers explain the request. At $93 million for 242 units, the building would cost roughly $384,000 per apartment. A commercial real estate market report for the second quarter of 2026 put countywide apartment sales at about $132,136 per unit, with 13.0 percent vacancy and asking rents around $1,635 a month. New downtown rentals would have to cover a cost nearly three times what existing apartments sell for. The rebate is meant to help close that gap.
This is also the first application under the reinvestment policy the CRA adopted in Resolution 2025-083. The policy expects construction to be substantially complete within two years of permits. The applicant told staff a project this size can't be built in 24 months and submitted a longer schedule.
What the October 5 Vote Did and Didn't Do
The October 5 CRA meeting gave this project its momentum, though not a binding commitment. According to Florida Record's meeting summary, Agency Members Candace Rogers and Lorraine Koss moved to defer until the full board could review the non-confidential financial materials and possibly get outside analysis. That motion failed 5-2. The board then voted unanimously to have staff finish a draft TIF Incentive Agreement and bring it back at a later meeting, with the full non-confidential application package made public.
The draft wasn't on the CRA's November 2 agenda, which covered minutes, the annual report and a façade grant. That agenda lists the next meeting for December 7, 2026, at 6:00 p.m. Until the board approves an actual agreement, 430 Brevard is an application the board has told staff to keep working on.
The Hotel Is Further Along, and Its Next Step Has a Deadline
At 603 Brevard Avenue, 360 Hospitality Group plans a seven-story, 104-room Fairfield by Marriott with a rooftop bar and coffee shop. It would sit on 0.87 acres the CRA currently owns. The approval includes parking waivers and a $500,000 contribution toward off-site parking.
The hotel has moved through a series of approvals:
- May 6, 2026: The Planning & Zoning Board recommended the project to council, with one dissent.
- May 12, 2026: City Council approved the development agreement and conceptual plan 5-0.
- September 8, 2026: The CRA voted unanimously to amend the redevelopment agreement and close out Phase I and Phase II. That covered the hotel brand, the market feasibility study and Marriott Select Brands' sign-off on the conceptual plan.
- Phase III, now underway: Final engineering and site plan approval must happen within six months of the September vote. The CRA doesn't hand over its land until final site plan approval is granted. Florida Record's summary puts a possible certificate of occupancy at mid-2029.
That land transfer is the hotel's real commitment point. The city still owns the land, and the site plan clock runs into early 2027. A separate tax rebate request for the hotel would also need its own application. At the September meeting, Rogers asked whether the short-term economic analysis would be enough to support one, and staff and the city attorney said TIF remains a separate process with its own requirements.
Where Each Project Stands
| Project | What's planned | Latest action | What still has to happen |
|---|---|---|---|
| 430 Brevard Ave. | 242 apartments, up to 8 stories, 2,800 sq. ft. retail | Oct. 5, 2026: staff told to draft the rebate agreement | Board approval of a binding agreement; next CRA meeting is Dec. 7 |
| 603 Brevard Ave. | 104-room Fairfield by Marriott, 7 stories, rooftop bar | Sept. 8, 2026: Phases I and II closed out | Final engineering and site plan within six months, then land transfer |
| Cocoa Brightline station | New station plus about 4 miles of double track | Oct. 6, 2026: federal grant check presented | Final design and construction; officials cite 2030 at the earliest |
The station is the longest bet of the three. In August, the city announced a federal award to fund final design and construction of the Cocoa Multimodal Station, including about four more miles of double track. At the October check presentation, Florida Today reported a $56.48 million grant for the station and said city officials expect it could open as soon as 2030.
The Smaller Spending Moves Faster
The changes most likely to show up in the next year or two are smaller. The CRA's October 1 newsletter reports an August approval of a $140,555 Kimley-Horn task order to design the T-Dock, and a façade improvement grant of up to $20,000 for 513 S. Cocoa Blvd., Suite D. On October 5, the board moved $37,400 to pay for a structural analysis of the Riverfront Park band shell, which has rust and other wear after about 27 years. Kimley-Horn will do that work too. Another façade grant request of up to $20,000, for 226 King Street, was on the board's November 2 agenda.
The T-Dock design, the band shell study and the South Cocoa Boulevard grant are already authorized, and that money goes toward the riverfront and storefronts that give the Village its character.
What the County Numbers Say About Timing
The project calendar is moving while Brevard County's housing market is fairly flat. The Space Coast Association of REALTORS® September 2026 report put the countywide single-family median at $380,000 for September, up 0.5 percent from a year earlier. Closed sales were 818, down 2.5 percent, and supply was 3.5 months, down 20.5 percent. The county's townhouse and condo median was $272,500 in September, up 6.9 percent. Supply was 5.9 months, down 22.4 percent.
These are countywide figures, not Cocoa-only figures. They do show a market where prices have held about even while supply has tightened. Under those conditions, a seller near the Village may try to price in a hotel, an apartment building or a train station. As of this week, the apartment building's rebate agreement hasn't been approved, the hotel's land hasn't changed hands, and the station's earliest opening is about four years away.
Rental supply is also growing elsewhere in Cocoa. Allegra at Cocoa, a 13-building community at 4300 FL-524, held its grand opening in July with about 312 apartments. If 430 Brevard is built, its rents will compete with newer buildings like that one.
FAQ
Has the 430 Brevard apartment building been approved? No binding agreement has been approved. On October 5, 2026, the CRA board directed staff to complete a draft rebate agreement for a later meeting. The next scheduled CRA meeting is December 7, 2026.
Does the rebate come out of current Cocoa taxpayers' bills? Under the requested terms, payments would come from the new tax increment the building itself generates inside the CRA district, with 90 percent going to the developer and 10 percent kept by the CRA for 10 years.
When could the Fairfield by Marriott open? Florida Record's summary of the September 8 meeting cites a possible certificate of occupancy by mid-2029. That depends on final site plan approval first.
If you're pricing a home or condo near Cocoa Village and want to know how much a listing is counting on projects that haven't passed their deciding votes, Burningham Realty can compare it with recent local sales and the CRA calendar before you make an offer. Want to know what your own place near the Village is worth right now? Start with a free home valuation.